Keeping a Medical Office Open Through a Rainy-Season Roof Replacement
United Health Group | Redlands, CA
Project Snapshot
Project Type: United Health Group Medical Office
Scope: Full roof replacement, TPO and shingle systems
Size: 20,000 sq ft
Duration: 88 days, completed on time
Delta’s Role: General Contractor, with self-performed HVAC and electrical
Overview
2 West Fern needed more than a new roof. The existing roof was already leaking badly. The building was a fully operating medical office, and the replacement would run straight through fall and winter rains. Delta Construction & Mechanical served as general contractor and self-performed the HVAC and electrical scopes. We replaced 20,000 square feet of TPO and shingle roofing in 88 days, finished on schedule, and never disrupted building operations.
The Challenge
An occupied building with an already-failing roof. Staff and patients were in the building every day, and the old roof was leaking before work began. Protecting the interior was urgent from day one.
Rainy-season timing. The client wanted the project delivered as quickly as possible, but fall and winter rains made compressing the schedule unrealistic. The real challenge was keeping the original timeline on track while working through repeated storms on an open roof.
A power shutdown in a medical facility. The electrical scope required cutting power to the building. For a medical office with critical data systems, going offline wasn’t an option.
The Approach
Phased in two sections. Delta split the roof into two phases. That limited how much of the building was exposed at any time and let the facility keep running underneath the work.
Constant communication. Our team spoke with tenants daily, met with building management three to four times a week, and checked in with the owner weekly. Everyone knew what was happening, when, and why.
Weekly safety meetings. Every week, crews reviewed the work ahead and the safety plan for an occupied site. The project finished with zero safety incidents.
On site through every storm. Whenever it rained, Delta’s crew was on the roof. The team dried in exposed areas, protected the building, and cleared pooling water. More than once, our team stayed overnight in the building to push water off the roof and clean up and repair water damage before staff arrived the next morning.
Self-performed HVAC and electrical. Because the mechanical and electrical work stayed in-house, Delta disconnected and reset the rooftop units on our own schedule. There was no waiting on outside subcontractors during a tight, weather-driven timeline.
The Solution: Zero Downtime During the Power Transfer
The electrical scope required shutting off power and transferring the building to its new service. To keep the facility online, Delta scheduled the work for a weekend, when no patients were on site, and ran the building on its backup generator throughout.
The owner’s data team wanted proof the backup system would hold. So Delta ran the generator switchover twice before the final cutover. When the time came, power transferred to the new service without incident, and the building never went offline.